For Projects

Information about the Peatland Code for peatland restoration projects - including how to apply

Image: Sphagnum © Norrie Russell

For Projects

Watch an introduction to the Peatland Code for those wishing to develop a peatland restoration project:

 

If you have decided to undertake a peatland restoration project and would like to become Peatland Code validated, and later verified, the following steps outline the process.

PC timeline

Step 1 - Establish eligibility 

Download the Peatland Code and establish if your project is eligible.  

For a project to be eligible for validation/verification to the Peatland Code (at present) the following basic pre-requisites must be met:


•    Peat soils must be greater than 30cm in depth for bogs with additional requirements, 45cm in fens
•    Peatland type must be blanket, raised bog or fen
•    Peatland condition must be 'Actively Eroding', 'Drained', ‘Modified bog’, ‘Cropland – drained’, ‘Grassland - intensive’                                                                                     ‘Grassland - extensive’ or ‘Modified fen’ (See Field Protocol for definitions)
•    Restoration activities must not include forestry removal
•    Restoration must not be legally or contractually required
•    Project must be able to enter a minimum contract of 30 years
•    Restoration activities must not conflict with any other land management agreements
•    Project must be additional i.e. it must require carbon finance to take place


These eligibility requirements are to be used as a quick indication of eligibility only. Full details can be found within the Peatland Code. 

Before embarking on the following steps projects may wish to consult a Project Developer. Please note Project Developers provide a paid service and will charge a fee. 

Step 2 - Register the project on the UK land carbon registry

If working with a Project Developer they will register the project. 

Create a IHS Markit, now a part of S&P Global, account and register the relevant project (please see the User Guide). You can also search the public register

For more information on the Registry and associated fees please see the Peatland Code Registry section of this site.


Step 3 - Complete Peatland Code documentation

Complete a field survey of the project site and complete the required Peatland Code documentation

To demonstrate compliance with the requirements of the Peatland Code a number of actions and forms must be completed. The documents, available to download below, provide all the information required to carry out this step:

For all projects see Peatland Code Guidance, Clarification Document and Field Protocol

Fens 

 

 

Bogs

Extension Requests

During the Peatland Code Project Plan/Restoration Validation or Verification process you may apply for an extension. Requests are submitted via the Extension Request Form and are not guaranteed for approval, they are considered on a case by case basis. Please apply with as much advance notice as possible.

Step 4 - Project Plan validation

Contact an appointed validation body to carry out your project validation. This is a paid service, for quotes please contact the validation bodies directly.

The current bodies approved to validate and verify Peatland Code projects are OF&G, and Soil Association for more information on our Validation and Verification bodies (VVB) see here. Upon application a date to conduct audit of both the project site and the project documentation will be arranged. Amendments to the project plan may be required if determined necessary by the validation/verification body to ensure compliance with the Peatland Code

The validator submits directly to the Peatland Code team all the documents required for a validation review. At this stage, the validator has already performed their checks and had detailed contact with the Project Developer. The validator sending through the documents is confirmation that they believe the project should be validated to the Peatland Code.

Step 5 - Peatland restoration

Secure funding and start/complete restoration activity as per Project Design Document. 

A public register of all available Peatland Code projects is available online, allowing potential buyers to search for one that meets their requirements. Alternatively, projects can use the services of a specialist carbon broker to actively search for a buyer on their behalf. A sale can also result from a direct relationship, for example between a land manager/owner and a local business. Projects can sell the climate benefits at any time. By marketing the additional benefits that arise alongside the climate benefits of peatland restoration it may be possible to achieve a greater purchase value. 

Step 6 - Restoration validation

Within one year of finishing the restoration activities detailed in the Project Design Document the Project must arrange an independent Validation / Verification body to assess the restoration work on site. This validation of the restoration activity will check if the project has delivered the planned restoration work to a good standard and adjust the expected emission reductions if necessary. A ‘Restoration Validation’ certificate is awarded stating the amount of expected emission reductions and the corresponding number of Pending Issuance Units (PIUs). If Pending Issuance Units were issued before restoration commenced these can be adjusted according to the Restoration Validation certificate. 

 

Step 7 - Verification

Following successful validation and completion of the restoration activity a regular schedule of verification audits will be conducted by the validation/verification body. This will ensure the project achieves and maintains the expected condition category change, delivering the expected greenhouse gas benefit over its duration. The project must submit a Project Progress Report to the verification body.

 

Peatland Code Grievances:

The IUCN UK PP is committed to ensure that the grievance and appeal process is as transparent and fair as possible. If you have any of the grievances related to the application of the Peatland Code please complete this form with as much information as possible and email it to the info@iucn.org.uk and copy in the peatlandcode@iucn.org.uk. Our disputes coordinator will then confirm receipt of your grievance within 15 working days and assign you a unique reference number. More information on our appeals and grievance process can be found here.

 

Peatland Code logo

'Work in progress' sign with a digger on it next to two photographs of children drawing on large sheets of paper
The Power of the Peat Bogs! How pupils turned their environmental education into a song Primary school pupils who have engaged with a project to restore ancient peatland and traditional…
SWPP award
South West Peatland Partnership awarded gold by Global Good AwardsThe South West Peatland Partnership won a Gold award at the Global Good Awards for their work…
Exterior view of Virtual Peatland Pavilion showing four large domes in a desert landscape
Seeking content for the COP29 Virtual Peatland PavilionThe IUCN UK Peatland Programme and Global Peatlands Initiative are seeking new content for an…
Peatland at Inshriach, Allt a’ Mharcaidh
Largest ever gathering of UK peatland experts to celebrate ‘Peatlands, People and Nature’ in the Cairngorms National ParkAviemore in the Cairngorms National Park is to play host to the UK’s largest gathering of peatland…
Landscape of mountains and forest
View the full programme for #PeatConf24 and book your tickets now!The full programme for the IUCN UK Peatland Programme 2024 conference ‘Peatlands, People and Nature…
CivTech in white writing with blue background and outlines of scales, lightbulb and book
CivTech challenge invites ideas for Peatland Code and Woodland Carbon CodeProposals are being invited for the Scottish Government's CivTech Challenge 10.6 to use technology…
Talla Gameshope image
Changes to UK Land Carbon Registry feesFrom 1 November 2024, the fees charged to issue and convert units on the UK Land Carbon Registry…
Peatland with mountains on the background
Scottish peatland recognised as globally important by UNESCO World Heritage Site designation The Flow Country in the north of Scotland, Europe's largest expanse of blanket bog, has been…
Brown butterfly with black spots on pink bell shaped flower
New species showcase - large heathOur latest species showcase introduces the large heath butterfly, its association with two iconic…
Haresfoot cottongrass with blue sky in the background. Credit Laurie Campbell SNH
New briefing addresses the peatlands and methane debateThe IUCN UK Peatland Programme has launched a new briefing “Peatlands and Methane” that summarises…
Peatland with mountains in the background
New £3 million fund for peatland restoration in Northern IrelandApplications for the new £3million Peatland Challenge Fund to help protect Northern Ireland's…